Nepal has secured approval from India's Central Electricity Authority to import up to 350 MW of power from the Indian Energy Exchange to manage winter energy deficits caused by seasonal low river flows and flood-damaged hydropower projects

Vikram Misri in Kathmandu
India's Foreign Secretary Vikram Misri during a meeting with Nepal's Foreign Affairs Minister Shisir Khanal, at the Ministry of Foreign Affairs, in Kathmandu. | Photo: @MofaNepal/X via PTI
Summary of this article
  • India authorized Nepal to import up to 350 MW of electricity to bridge seasonal winter supply shortages.

  • The approval covers the period from November 17, 2026, through July 31, 2027.

  • Electricity will be sourced using multiple cross-border transmission lines to offset drops in domestic hydropower generation.

Nepal has received approval to import up to 350 MW of electricity from India this winter to meet domestic power demand amid a decline in hydropower generation and damage to several projects caused by recent floods.

The Central Electricity Authority (CEA) under India's Ministry of Power has authorised the Nepal Electricity Authority (NEA), the state-owned power utility, to procure electricity at competitive rates from the Indian Energy Exchange (IEX) for up to 17 hours a day, NEA officials said.

The approval is valid from November 17, 2026, to July 31, 2027, and is expected to help Nepal manage the seasonal gap between electricity demand and domestic generation, NEA Managing Director Dirghayu Kumar Shrestha said.

Of the approved 350 MW, Nepal can import 300 MW through the Kataiya-Kushaha, Ramnagar-Surajpura and Raxaul-Parwanipur transmission lines. The remaining 50 MW can be sourced through the New Nautanwa-Mainahiya transmission line.

Nepal's dependence on run-of-the-river hydropower projects makes electricity generation highly seasonal.

While rising river flows during the summer months enable the country to generate surplus power for export, mainly to India, declining water levels during winter significantly reduce domestic production, forcing it to rely on imports.

The country's power supply situation has also been affected by the damage caused to several hydropower projects in central Nepal during the devastating Rasuwa-Bhotekoshi floods in August.

Projects with a combined installed capacity of 431 MW have remained disconnected from the national grid following the disaster.

However, domestic generation is expected to improve from mid-April as water levels in rivers gradually rise, reducing Nepal's dependence on imported electricity and potentially allowing it to resume exports, officials said.

×