Advertisement
Saturday, Oct 16, 2021
Outlook.com
Outlook.com

Over 400 Infrastructure Projects Show Cost Overruns Of Rs 4.34 Lakh Cr

Reasons include delay in land acquisition, delay in obtaining forest and environment clearances, lack of infrastructure support and Covid-19, amongst other hindrances.

Over 400 Infrastructure Projects Show Cost Overruns Of Rs 4.34 Lakh Cr
Representational Image | PTI
Over 400 Infrastructure Projects Show Cost Overruns Of Rs 4.34 Lakh Cr
outlookindia.com
2020-12-27T12:55:30+05:30

As many as 442 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns of over Rs 4.34 lakh crore, reports claimed.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above.

Of the 1,671 such projects, 442 reported cost overruns and 536-time escalation.

"Total original cost of implementation of the 1,671 projects was Rs 21,21,383.82 crore and their anticipated completion cost is likely to be Rs 25,55,957.52 crore, which reflects overall cost overruns of Rs 4,34,573.70 crore (20.49 per cent of original cost)," the ministry's latest report for November 2020 said.

The expenditure incurred on these projects till November 2020 is Rs 11,93,997.81 crore, which is 46.71 per cent of the anticipated cost of the projects.

However, it said that the number of delayed projects decreases to 412 if the delay is calculated on the basis of latest schedule of completion.

Further, the report said that for 942 projects neither the year of commissioning nor the tentative gestation period has been reported.

Out of 536 delayed projects, 120 projects have overall delay in the range of 1-12 months, 134 projects have a delay of 13-24 months, 162 projects reflect a delay in the range of 25-60 months and 120 projects show delays of 61 months and above.

The average time overrun in these 536 delayed projects is 44.15 months.

Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing; delay in finalisation of detailed engineering; change in scope; delay in tendering, ordering and equipment supply; and law and order problems, among others, are the other reasons, the report said.

The report has also cited ''state-wise lockdown due to Covid-19'' as a reason for the delay in implementation of these projects.

Project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are under-reported, the report stated. 

Advertisement

Outlook Newsletters

Advertisement
Advertisement
Advertisement

Read More from Outlook

Global Hunger Index 2021: What It Means For India?

Global Hunger Index 2021: What It Means For India?

India has slipped to 101st position from last year’s 94th position

Lynching, Chopping Off Hand Was 'Punishment' For 'Desecrating' Holy Book: Nihang

Lynching, Chopping Off Hand Was 'Punishment' For 'Desecrating' Holy Book: Nihang

A man wearing the blue robes of the Sikhs’ Nihang order appeared before the media, claiming that he had 'punished' the victim for 'desecrating' a holy book.

Dhoni's CSK Blow Away KKR To Win 4th IPL Crown

Dhoni's CSK Blow Away KKR To Win 4th IPL Crown

Chennai Super Kings defended their 192/3 as Kolkata Knight Riders suffered a batting collapse after a solid start to lose by 27 runs.

Army Says Poonch Operation Is On

Army Says Poonch Operation Is On

The Army has said a counter-terrorist operation is in progress in the area of Nar Khas forest in Mendhar, Poonch district, since the evening of October 14.

Advertisement